Day 1 installation
Day 1 takes the store from “hardware arrived” to “system ready to activate”. Adapt timing to the store’s opening hours.
Recommended sequence
Section titled “Recommended sequence”- Kick-off with the store contact (areas, aisle priorities, constraints).
- Base Station mounting (power, network, position).
- Mount installation per floor plan / map.
- Tag placement on mounts.
- Activation / association of tags ↔ items in the app.
- Proximity test on a sample.
- Remote test (if Base Station is in scope) on near/far samples.
- Quick training for key staff.
- Handover with open items and go-live plan.
What to bring
Section titled “What to bring”- App installer (official hub) on the work laptop
- Location credentials
- SKU list / printed map or tablet
- Spare tags and mounts
- Basic tools (ladders per store policy, etc.)
“Day 1 ok” criteria
Section titled ““Day 1 ok” criteria”| Criterion | Ok if… |
|---|---|
| Base Station | Online and associated |
| Sample tags | Update in 60–80 s |
| Staff | Can perform a simple price change |
| Open items | Listed with owner and date |
Then: Go-live.